In early November, a reader asked Dock Line Magazine something a lot of Magnolia drivers have asked: when will the roadwork at FM 1488 and FM 1774 be finished? The magazine's answer depends on which side of FM 1774 the reader means. West of the intersection, the widening is close to done. Starting at FM 1774 and running east through town, the current target is late 2027.
If you're comparing neighborhoods in Magnolia, that answer is more useful than any one completion date. FM 1488 is the road most of these neighborhoods use to reach The Woodlands and I-45, and it is being rebuilt as separate jobs on separate schedules. Where a subdivision's entrance meets FM 1488 tells you whether you're moving onto a finished road or into more than another year of lane shifts, and the road that would take through traffic out of town entirely is a project for the 2030s.
One road, separate contracts
TxDOT treats FM 1488 through Magnolia as two widening jobs that meet at FM 1774. Further east, toward Interstate 45, a third project adds raised medians.
| Stretch of FM 1488 | What's being built | Where it stands |
|---|---|---|
| Waller County line to FM 1774, about 3.79 miles | Widening, TxDOT project 0523-08-007 | In its final stages during 2026 |
| FM 1774 to just west of FM 149, about 4.03 miles | Rebuilt from two lanes to four, TxDOT project 0523-09-009 | 70.29% complete as of a May 8, 2026 contractor estimate; target late 2027 |
| Mostyn Drive to I-45, through FM 2978 | Raised medians that replace open left turns | A separate safety project |
Because the two widening contracts meet at FM 1774, Dock Line points out, that intersection looks like the middle of one enormous project when the work on either side has really been running on two separate clocks. For a buyer, the western clock has nearly run out. The in-town clock still has more than a year to go.
Why the in-town date keeps moving
Some online records still list December 2026 as the finish date for the in-town job. That date comes from a state filing registered in July 2021, which assumed construction would start on August 1, 2021. According to Dock Line's review of TxDOT contract records, the notice to proceed came on March 16, 2022, and physical work began on June 14, 2022, more than ten months after the date in that filing.
James Construction Group won the contract with a bid of about $48.29 million, and the job was planned around 622 working days. The May 8, 2026 TxDOT contractor estimate put the work at 70.29% complete, with 129.58% of the allotted contract time used and an adjusted projected cost of about $49.21 million. Contract time is counted in charged working days, so the 129.58% figure doesn't mean crews have worked 130% of every calendar day. It does explain why the old date no longer matches what drivers see. Magnolia's city engineer had pointed to the third quarter of 2027, and later progress reporting based on TxDOT updates pushed the target toward the fourth quarter.
The Houston Chronicle reported in March 2026 that the FM 1774 to FM 149 widening was expected to finish by mid-2027. The November Dock Line report is the more recent of the two and gives late 2027. In the Chronicle story, Precinct 2 Commissioner Charlie Riley pointed out that the county isn't responsible for FM 1488. He said state road projects involve relocating major utilities, redesigning drainage, coordinating with railroads and getting environmental approvals. Dock Line points to the same list, which is why the corridor can't be rebuilt in one pass while it keeps carrying local traffic.
New lanes can also open before the full contract is finished. That's why a stretch can look complete while the next stretch still has a traffic shift, a driveway being adjusted or a drainage crew at work. A home that looks out on finished pavement can still be on an unfinished project.
The neighborhoods on the in-town clock
City of Magnolia traffic notices list the in-town work by cross street. A fall 2025 traffic switch moved drivers onto new pavement on the south side of FM 1488 from just west of Audubon Boulevard, through the SH 249 intersection, to just east of Magnolia Ridge Boulevard. The following weekend's switch ran from Mill Creek Road to Audubon Boulevard, with paving through the Audubon Boulevard intersection. In March 2026, the Houston Chronicle reported that TxDOT was opening four lanes, two in each direction, from Magnolia Ridge to Mill Creek Road.
Those street names line up with communities buyers are touring now. Magnolia Ridge, an M/I Homes community, is reached from FM 1488 by Magnolia Ridge Boulevard, and the builder's community page lists pricing from $199,990. D.R. Horton's Mill Creek sits at Mill Creek Road off FM 1488, about five miles west of FM 2978, with one- and two-story homes listed from $224,990 on the builder's community page. Audubon Boulevard and the SH 249 intersection are inside the same work zone.
When you compare a home in one of these neighborhoods with a similar home elsewhere, the late-2027 target is part of the comparison. Buy this winter and the first year or more of your commute goes through an active work zone. The finished four-lane road is coming, and you'd be in place when it opens. Buyers who would rather skip the work zone can look west of FM 1774, where the widening is in its final stages.
East of town, the work changes how you turn
Toward The Woodlands, the issue is turning, because this project adds no lanes. Community Impact described the Mostyn Drive to I-45 project, which runs through the FM 2978 intersection, as raised medians between 1 and 14 feet wide, built from west to east, with five new traffic signals proposed by TxDOT. TxDOT spokesperson Leo Flores told the Houston Chronicle that converting a two-way left-turn lane to a raised median reduces the "conflict points" where vehicles can cross paths.
If you're looking on this stretch, drive the route at the hours you'd actually commute. Note whether the subdivision exit lets you turn directly toward I-45 or sends you to a signal or a U-turn first.
This end of the corridor is also where much of the area's shopping has opened. Community Impact counted more than 80 businesses opened since 2022 along FM 1488 between Abney Lane and Hwy. 242, including H-E-B, Starbucks and Lowe's, as of its April 2025 report. For many households on this side of Magnolia, everyday errands mean trips along the median corridor, on top of the commute.
The bypass is a 2030s road
The longer-term answer to through traffic is the Magnolia Relief Route. TxDOT describes it as a new four-lane divided highway of about 5.4 miles, running from FM 1488 west of Magnolia to SH 249 east of town, with grade-separated crossings at FM 1774, the Union Pacific Railroad and SH 249. The Houston-Galveston Area Council's FY2026 10-Year Plan, published in November 2025, schedules advance right-of-way acquisition for 2030 with $14.21 million in state funding, and construction for 2034 with $90.62 million in total funding.
For a household buying this winter, that sets the timeline. The four-lane widening through town is what will ease the in-town commute over the next few years. The relief route is planned for construction about eight years from now, so it's a reason to be optimistic about downtown Magnolia over the long run, and it shouldn't factor into a commute you'll be making in 2027.
Other routes in the meantime
Some relief may come sooner on the east side. In April 2026, Montgomery County approved a $6.15 million contract for about 2.05 miles of Woodtrace Boulevard, from Highland Drive to FM 2978, including a bridge over Dry Creek. The contract documents call for substantial completion within 365 calendar days. The Westwood Magnolia Parkway Improvement District says Woodtrace is meant to become an east-west connection to SH 249, and it reported its own section, from FM 2978 to Dobbin-Hufsmith, finished as of its November 2023 update. For homes near FM 2978, Woodtrace may eventually be a way to reach SH 249 without using FM 1488.
The same planning applies across Magnolia. Before you compare price per square foot, find where the neighborhood's entrance meets FM 1488 and match it to the table above. Two homes at the same price can come with very different first years of driving. If you're also weighing a Magnolia address against a Woodlands one, our Magnolia vs. The Woodlands market comparison covers the prices. Fall traffic is a separate issue, and our post on Renaissance Festival weekends covers how they add to the load on FM 1488.
Quick answers
Is FM 1488 finished west of FM 1774? That section, from the Waller County line to FM 1774, was in its final stages during 2026.
When will the in-town widening be done? The most recent target is late 2027, for the stretch from FM 1774 to just west of FM 149. Dock Line describes that as a target, not a promise, since weather, utility conflicts and drainage work can still change the schedule.
Will the relief route take traffic off FM 1488 soon? Not soon. The regional plan schedules construction for 2034, with right-of-way acquisition in 2030.
If you're deciding between neighborhoods on different sides of FM 1774, Eve Kneller can go through how each one connects to FM 1488, drive the commute with you at the hours you'd make it, and help you price that into your offer. Request your free CMA & consultation, or start with our Magnolia neighborhood guide.